120-year-old cast iron pipeline

The pipeline runs 1.2 kilometres along a main road

System

Rehab

Medium

Water

Application area

Utility

Line type

Transport line

Country

Germany

Region

Rhineland-Palatinate

Situation

Since the pipeline runs along the busy Homburger Straße, traffic had to continue to flow during the construction works.

Special features

Feeding length of more than 1,000 metres required

Passing through several bends up to 45°

Heavy incrustations of the existing pipeline had to be removed

Technical details

Material of host pipe

Ductile cast iron, year of construction 1900

Diameter of host pipe

DN 300

Transported fluod

Potable water

Operating pressure

10 bar

Total length

1,220 m

Number of sections

2 rehabilitation sections

Number of bends

5

Installation time

12 working days

Why Primus Line?

Small footprint

The small footprint with small and few excavation pits was an important factor for the client.

Short rehabilitation time

The short rehabilitation period along the busy road led only to minor disruptions.

Extended lifetime of the existing pipeline

A sustainable rehabilitation with a service life extension of the existing pipeline by at least another 50 years was the decisive factor.